Applications of Statistical Methods in Civil Engineering
(Return to Statistical Playground)

Situations provided by: Prof. Don Coduto, Civil Engineering Department, Cal Poly Pomona

Edited by: Prof. Phil Rosenkrantz, Industrial and Manufacturing Engineering Department, Cal Poly Pomona

The following situations are examples from the field of civil engineering where variation occurs and statistical method either are or could be applied. In some instances the current practice may not be very sound based on statistical theory. These applications are useful for analyzing and discussing the use of statistics in the practice of civil engineering.

Table of Contents

Traffic/Transportation Engineering
Surveying and Mapping
Structural Engineering
Earthquake Engineering/Seismology
Hydrology
Environmental Engineering
Geotechnical Engineering
Traffic/Transportation Engineering
Sanitary Engineering
Traffic/Transportation Engineering
Coastal and Port Engineering


Traffic/Transportation Engineering

Given: Distribution of hourly traffic volume on a proposed highway

Find: The hourly volume to be used for design

Commentary: The design volume dictates the required number of lanes, etc. For most highways, the design volume is that which corresponds to the 30th busiest hour in the year.

Discussion: What are the ramification of using this "rule of thumb" for estimating the design volume? How can the "distribution" affect how the rule works (ie. distribution of interarrival times: normal vs. exponential),

For Further Study: Queuing Theory

(Return to Table of Contents)


Surveying and Mapping

Given: A series of measurements from the field, each of which is made using an instrument that has a certain precision.

Commentary: Many measurements in surveying are made using a series of instrument setups. For example, consider a piece of property whose boundary consists of 8 line segments. The orientation of one of these segments with respect to true north is known to a precision of 20" of arc. A surveyor sets up a "total station" (an instrument that measures angles and distances) at each of the 8 corners, and measures the angles to a precision of 20" and the distances to a precision of 0.01 ft. These measurements are then "adjusted" so that satisfy the rules of geometry.

Find: The precision of the computed orientations of the other property lines. It is not 20"!

For Further Study: "Precision" and "accuracy" are two very important aspects of measurement. Also see "Repeatability and Reproducibility (R&R) Studies".

(Return to Table of Contents)


Structural Engineering

Given: The Uniform Building Code dictates certain design values for the live load on building elements (live load is that load induced by furniture, inventory, occupants, moveable objects, etc., as contrasted to dead load (the structure itself), earthquake load, wind load, etc.). For example, the code-specified design load for classrooms is 40 lb/ft^2.

Find: The probability that this design load will be exceeded.

Commentary: I've seen some statistical data on live loads based on actual measurements in buildings. I couldn't find it in my files, but I think the COV is about 0.10, and the probability of exceeding is about 0.05.

A design method called "load and resistance factor design" (LRFD), which our students learn in a junior-level course, uses "load factors" and "resistance factors" that have been developed from extensive reliability analyses. Although design engineer simply uses the specified factors in a typical design, it is important to understand how the building codes developed them.

(Return to Table of Contents)


Earthquake Engineering/Seismology

Given: A proposed dam to be built at a certain site, the probability of earthquakes of various sizes occurring on faults at various locations, the predicted peak horizontal ground acceleration at the dam site from each of these earthquakes.

Find: The design peak ground acceleration, which is the one that corresponds to a certain probability of being exceeded during the design life of the dam.

(Return to Table of Contents)


Hydrology

Given: Stream flow records for the Santa Ana River near Corona.

Find: The stream flow (ft^3/s) that corresponds to a particular recurrence interval. This flow can then be used to design dams, levees, etc.

Commentary: After a devastating flood in 1938, the Army Corps of Engineers built Prado Dam to protect Orange County. This dam and its spillway can be seen from the 91 freeway (the spillway has 1776-1976 painted on it). The reservoir behind this dam is normally empty, and is intended to capture the excess flood waters in the event of another major flood, thus keeping the stream flow below the dam at manageable levels. This dam was designed based on the best hydrologic data and analyses then available. However, subsequent analyses performed in the 1970s and 1980s found the flood that corresponds to a certain recurrence interval (200 years?) is much greater than had previously been considered. Such a flood could overtop the dam, causing it to fail, thus producing massive flooding in Orange County. Because of this, the Army Corps of Engineers is currently building a massive flood control project along the Santa Ana River, which includes a new dam upstream of Prado (Seven Oaks Dam), new levees, and the raising of Prado Dam. This is a massive construction project, all of which is based on a statistical analysis of hydrologic data.

(Return to Table of Contents)


Environmental Engineering

Given: A series of groundwater samples obtained at different locations and depths in an aquifer, and the concentration of a certain chemical in each sample.

Find: The probability that the concentration at any point in the aquifer exceeds some specified value.

(Return to Table of Contents)


Geotechnical Engineering

Given: Four soil samples obtained from a certain stratum of soil and the results of laboratory consolidation tests on each sample. These test results are used to compute the settlement that will occur if a certain load is placed on this strata.

Find: Considering only variations due to the sample locations (i.e., assuming the sampling method, testing, and analysis introduce no uncertainty), compute the probability that the settlement will exceed some specified value.

Commentary: I've seen data that indicate COV values of 0.26 to 0.52 from multiple samples obtained from "homogeneous" strata. Thus, analyses based on mean values could produce results that are seriously in error.

Related analysis: Given the cost of sampling and testing, how many samples should be taken

(Return to Table of Contents)


Traffic/Transportation Engineering

Given: An access road for a new recreation area is to have a toll booth. The distribution of vehicles per minute, the time required to process each vehicle, and the length of roadway required for each waiting vehicle are given.

Find: The required "storage area", which is the minimum required length of roadway between the toll booth and the adjacent highway such that the probability of waiting vehicles extending onto the highway does not exceed a certain value.

Commentary: The acceptable probability depends on the consequences of being exceeded. For example, if the highway is a busy one-lane road, a very low design value would be used, whereas if it is a low-volume four-lane road, perhaps a higher probability would be acceptable.

A similar analysis also could be done based on the probability of exceeding some maximum acceptable waiting time.

Based on the results of such analyses, we might decided to have more than one toll booth. If so, how often would both booths need to be in service?

For Further Study: Queuing Theory (study of waiting lines)

(Return to Table of Contents)


Sanitary Engineering

Given: A series of samples of wastewater ("water" from a sewer) and results of biological oxygen demand (BOD) tests

Find: The design BOD, which is the value that corresponds to a certain probability of not being exceeded. This value would be used to design the wastewater treatment plant.

Commentary: A deterministic approach would use the mean BOD and apply some factor of safety.

(Return to Table of Contents)


Traffic/Transportation Engineering

Given: An intersection between a residential street and a major artery in a suburban community. The residential street has a stop sign, but the artery does not.

Find: The probability that a vehicle stopped at the stop sign will have to wait more than a specified period before making a left turn onto the artery.

Commentary: If this probability is too high a traffic signal may be warranted. Traffic engineers perform this kind of analysis to determine where to place traffic signals.

For Further Study: Poisson processes. Interarrival times.

(Return to Table of Contents)


Coastal and Port Engineering

Given: Anticipated distribution of cargo ship arrivals at a port in the year 2010, and the mean time required for a ship to occupy a berth.

Find: The number of berths required so the probability of a ship having to wait more than a certain number of hours to enter a berth is no more than x.

Commentary: A large amount of construction is currently under way at the ports in Long Beach and Los Angeles. Portions of this construction would be based on these kinds of analysis.

For Further Study: Queuing Theory, Simulation

(Return to Table of Contents)