The project will create a raised intersection to bring the roadway to sidewalk level to make pedestrian presence more visible to motorists. The southbound right-turn lane from Mansion Lane to University Drive will be removed and the sidewalk reconstructed.
The completion of this project is scheduled for the last week of April, 2008; crews will start construction activities on March 22, following the end of the winter quarter in an effort to complete the entire construction during the spring break.
| Construction start date: | March 2008
|
| Expected completion date: | April 2008 |
| Construction Cost: | $169,000 |
| Total Project Cost: | $260,000 |
| Gross sq. footage: | NA |
| % of project complete: | 0% |