Contents
Cal Poly Pomona

October 2009 Updates

Retaining Wall Project - Building 112

The Kellogg House complex where the new reinforced concrete wall is being built. Click to Zoom. View of concrete retaining wall  from Kellogg Guest House.  Click to Zoom. New asphalt work at the site. Click to Zoom.
View of Guest House and new site infrastructure.  Click to Zoom. New storm drain catch basin at the retaining wall site. Click to Zoom. Slurry and painting of parking spots at lot R. Click to Zoom.

About This Project

The Retaining Wall project is located at Building 112 at the Kellogg Guest House and includes the renovation of an existing retaining wall built in the early 1930s by the Kellogg Family. The scope of work of this project includes the construction of a reinforced concrete wall intended to secure the south east foundations of the Guest House Building and to avoid unsafe slippage of existing stones from the aged wall to the road. The project demands relocation and replacement of existing infrastructure such as water, sewer, electrical, irrigation, gas, fire alarm and voice/data.

This $200,000 project will provide a safe and solid retaining wall to the Kellogg Guest House. The project was started on July 27th and is expected to be finished by mid September 2009 during the summer season. Intense coordination has been made with the Kellogg West administration for the implementation of this project.

Statistical Information

Construction start date:
July 2009
Expected completion date:
Sept 2009
Construction Cost:
$140,000
Total Project Cost: $200,000
Gross sq. footage:
500
Assignable sg. footage addition:
500
% of project complete:
100%

Project Funding

  • Funding for this project is from Special Repair budget.

Progress of Major Construction Activities

  • New 4” asphalt coat at adjacent road is completed.
  • Existing gate to radio tower and upper reservoir is installed.
  • All infrastructure to the Guest House including, telecom, electrical, water, sewer systems and irrigation has been reconnected.

Key/Critical Issues Currently Pending

  • NA at this time.

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance

  • NA at this time.