Contents
Cal Poly Pomona

July 2010 Updates

Residential Suites Phase II

Construction Zone 2: Construction of new Commons west of Building 54. Click to Zoom. Construction Zone 1:  Completed construction of parking Lot Q in the foreground and Building 62 and 63 in the background. Click to Zoom. Construction Zone 2:  New Playground at Child Care Center. Click to Zoom.
Construction Zone 2: An additional view of the new Child Care Center’s playground. Click to Zoom. Construction Zone 2: Building 54 with view of the Bronco Horse Statue with the Commons in the foreground. Click to Zoom. Construction Zone 2: North elevation of Building 54 (south of the Child Care Center’s playground). Click to Zoom.

About This Project

The Residential Suites Phase II project is a complex of three (3) student housing facilities (Buildings A, B, & C), a commons facility (Building D) and site improvements. This project is located within the boundaries of Kellogg Drive, Eucalyptus Lane, parking lot G, baseball field, Gymnasium Building. It is adjacent to the Residential Suites Phase I, which were constructed in 2004.

The project has a total of approximately 255,500 SF new construction with 622 beds in different suites layout with living room and kitchen. The student housing facilities are wood-framed Type V, 1-Hour buildings, three and four stories in height. Generally, they are organized with dwelling units situated along double-loaded corridors served by common elevator/entry lobbies. General study lounges, administrative areas, and service rooms are located adjacent to the elevator lobbies on each floor. The buildings are clad primarily in stucco, and feature both pitched and flat roofs (clad in composite shingles and built-up roofing, respectively).

The one-story commons facility houses a convenience store/cafe' and a multi-purpose meeting room. Classified as Type V, NR building, this one story structure utilizes both steel and wood framing. Befitting its public nature, the building is clad primarily in glass with both stucco and concrete masonry accents. Pitched roofs are standing seam metal, while the built-up flat roof hosts the facility's mechanical equipment.

An expansion to the Phase I project's mechanical plant provides the chilled and hot water for the four pipe mechanical systems that serve the new buildings. Full electrical, plumbing, and life safety systems and telecommunication infrastructure are provided. Site improvements include the courtyard spaces formed by the housing facilities (a combination of planting and hardscape materials), plazas adjacent to the commons facility, a parking lot, and related vehicular and emergency access ways.

Statistical Information

Construction start date:
June 16, 2008
Expected completion date:
Summer 2010
Construction Cost:
$56,329,793
Total Project Cost: $75,778,800
Gross sq. footage:
225,500
Assignable sq. footage:
183,500
% of project complete:
100%

Project Funding

  • Funding for this project is from University Housing Services a department of Student Affairs Division, utilizing a system wide revenue bond with repayment from unit rental income.

Progress of Major Construction Activities

  • Site Development:
    All contract work is complete at this time.
  • Building Construction:
    All contract work is complete at this time with minor exceptions. Warranty tickets are being opened for various items.

Key/Critical Issues Currently Pending

  • Complete playground construction and the re-opening of a portion of Eucalyptus Lane so that permanent access to Lot G is from Red Gum Lane. This remaining work will be completed by our own Facilities personnel.

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance

  • NA at this time.