Cal Poly Pomona

November 2009 Updates

Residential Suites Phase II

Construction Zone 1 -  Building C3 is 95% complete.  Exterior sitework including sidewalk and tree installation in progress. Click to Zoom. Construction Zone 1— Buildings B2 is 70% complete. Exterior  & interior painting, woodwork and finishes in progress. Click to Zoom. Construction Zone 1— Building C1 is 95% complete.  Interior finishes in progress. Click to Zoom.
Construction Zone 1— Building D, storefront window installation is 90% complete.  Exterior stucco work in progress. Click to Zoom. Construction Zone 1 - Quad sitework in progress.  Tree planting and sidewalk installation in progress. Click to Zoom. Construction Zone 1– Building B2 study room drywall and interior painting touch-up work in progress. Click to Zoom.

About This Project

The Residential Suites Phase II project is a complex of three (3) student housing facilities (Buildings A, B, & C), a commons facility (Building D) and site improvements. This project is located within the boundaries of Kellogg Drive, Eucalyptus Lane, parking lot G, baseball field, Gymnasium Building. It is adjacent to the Residential Suites Phase I, which were constructed in 2004.

The project has a total of approximately 255,500 SF new construction with 622 beds in different suites layout with living room and kitchen. The student housing facilities are wood-framed Type V, 1-Hour buildings, three and four stories in height. Generally, they are organized with dwelling units situated along double-loaded corridors served by common elevator/entry lobbies. General study lounges, administrative areas, and service rooms are located adjacent to the elevator lobbies on each floor. The buildings are clad primarily in stucco, and feature both pitched and flat roofs (clad in composite shingles and built-up roofing, respectively).

The one-story commons facility houses a convenience store/cafe' and a multi-purpose meeting room. Classified as Type V, NR building, this one story structure utilizes both steel and wood framing. Befitting its public nature, the building is clad primarily in glass with both stucco and concrete masonry accents. Pitched roofs are standing seam metal, while the built-up flat roof hosts the facility's mechanical equipment.

An expansion to the Phase I project's mechanical plant provides the chilled and hot water for the four pipe mechanical systems that serve the new buildings. Full electrical, plumbing, and life safety systems and telecommunication infrastructure are provided. Site improvements include the courtyard spaces formed by the housing facilities (a combination of planting and hardscape materials), plazas adjacent to the commons facility, a parking lot, and related vehicular and emergency access ways.

Statistical Information

Construction start date:
June 16, 2008
Expected completion date:
Summer 2010
Construction Cost:
$56,329,793
Total Project Cost: $75,778,800
Gross sq. footage:
225,500
Assignable sq. footage:
183,500
% of project complete:
87%

Project Funding

  • Funding for this project is from University Housing Services a department of Student Affairs Division, utilizing a system wide revenue bond with repayment from unit rental income.

Progress of Major Construction Activities

  • Site Development
    Overall site demolition is 96% complete. New construction is 99% complete. Zone 1 and 2 roadwork is 50% complete. Sidewalks and landscape is in progress.
  • Building Color-coat
    Color coat is complete on all buildings with the exception of exterior facades at common area for
    building B2 and exterior walls at building D.
  • Interior Construction
    Drywall is complete on all buildings with the exception of building A1 and D.
    Painting is in progress for building A1; buildings A2 and A3 are complete.
    Interior finishes including cabinet, countertops and flooring is complete in all buildings except for
    building A1.
  • Exterior Building Shell
    All buildings are water tight except for building D.

Key/Critical Issues Currently Pending

  • Implement of Stage 4 construction (Phase IV) work is near completion. Stage 5 (Phase V) work has commenced with the stage construction.

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance

  • NA at this time.