October 2009 Updates

Residential Suites Phase II

Construction Zone 1 -  Building C2 terrace is 95% complete.  Exposed soffit and storefront windows are complete. Click to Zoom. Construction Zone 1— Buildings B2 & B3 exterior work is complete; interior painting and woodwork in progress. Click to Zoom. Construction Zone 1— Interior painting and cabinet installation is complete.  Zone 1 quad work in progress. Click to Zoom.
Construction Zone 1— Building D, CMU block work is complete;  roof and storefront window installation in progress. Click to Zoom. Construction Zone 2 - Building A1 terrace work in progress; storefront windows are complete. Click to Zoom. Construction Zone 2– Building A1 color coat is complete. Interior drywall, cabinet and counter top work is in progress. Click to Zoom.

About This Project

The Residential Suites Phase II project is a complex of three (3) student housing facilities (Buildings A, B, & C), a commons facility (Building D) and site improvements. This project is located within the boundaries of Kellogg Drive, Eucalyptus Lane, parking lot G, baseball field, Gymnasium Building. It is adjacent to the Residential Suites Phase I, which were constructed in 2004.

The project has a total of approximately 255,500 SF new construction with 622 beds in different suites layout with living room and kitchen. The student housing facilities are wood-framed Type V, 1-Hour buildings, three and four stories in height. Generally, they are organized with dwelling units situated along double-loaded corridors served by common elevator/entry lobbies. General study lounges, administrative areas, and service rooms are located adjacent to the elevator lobbies on each floor. The buildings are clad primarily in stucco, and feature both pitched and flat roofs (clad in composite shingles and built-up roofing, respectively).

The one-story commons facility houses a convenience store/cafe' and a multi-purpose meeting room. Classified as Type V, NR building, this one story structure utilizes both steel and wood framing. Befitting its public nature, the building is clad primarily in glass with both stucco and concrete masonry accents. Pitched roofs are standing seam metal, while the built-up flat roof hosts the facility's mechanical equipment.

An expansion to the Phase I project's mechanical plant provides the chilled and hot water for the four pipe mechanical systems that serve the new buildings. Full electrical, plumbing, and life safety systems and telecommunication infrastructure are provided. Site improvements include the courtyard spaces formed by the housing facilities (a combination of planting and hardscape materials), plazas adjacent to the commons facility, a parking lot, and related vehicular and emergency access ways.

Statistical Information

Construction start date:
June 16, 2008
Expected completion date:
Summer 2010
Construction Cost:
$56,329,793
Total Project Cost: $75,778,800
Gross sq. footage:
225,500
Assignable sq. footage:
183,500
% of project complete:
85%

Project Funding

  • Funding for this project is from University Housing Services a department of Student Affairs Division, utilizing a system wide revenue bond with repayment from unit rental income.

Progress of Major Construction Activities

  • Overall site demolition is 96% complete. Framing in Construction Zone 1 & 2 is 99% complete.
  • Underground utility installation at Construction Zone 1 and 2 is 100% complete.
  • Building ‘D’ storefront windows are 90% complete. Color coat is complete on all buildings with the exception of exterior facades at common area for building B2.
  • Built-up roofing systems project wide are 100% complete. Interior drywall is complete on all buildings with the exception of building A1. Buildings A1, A2 and A3 painting is in progress. Cabinet and counter top installation is progressing for buildings A2 and A3. Carpet installation is in progress buildings A2 and A3.
  • LEED certification is on-going.

Key/Critical Issues Currently Pending

  • Implement of Stage 4 construction (Phase IV) work commenced on 9/22/09.

Upcoming Utility or Other Interruptions

  • Utilization of temporary chain link fence pedestrian paths are still active and will be throughout the remainder of the project. Irrigation tie in at Zone II is scheduled for October 30th, 2009.

Other Areas of Significance

  • NA at this time.