July 2009 Updates

Residential Suites Phase II

Construction Zone 1 -  Building C2/C3 store front window installation complete.  Minor exterior painting  has commenced. Click to Zoom. Construction Zone 1 - ‘Mock-up’ unit / Building C1 interior drywall complete; interior painting and cabinet installation in progress. Click to Zoom. Construction Zone 1— Buildings C2/C3 color coat completed; interior painting and cabinet installation in progress. Click to Zoom.
Construction Zone 1- Building B1/B2 framing is complete, lathing work has commenced; color coat is 80% complete on Bldg. B2. Click to Zoom. Construction Zone 1 - Building D steel erection completed; CMU walls and framing in progress. Click to Zoom. Construction Zone 2- framing completed, A1 exterior lath in progress; A2/A3 scratch/brown & window installation in progress. Click to Zoom.

About This Project

The Residential Suites Phase II project is a complex of three (3) student housing facilities (Buildings A, B, & C), a commons facility (Building D) and site improvements. This project is located within the boundaries of Kellogg Drive, Eucalyptus Lane, parking lot G, baseball field, Gymnasium Building. It is adjacent to the Residential Suites Phase I, which were constructed in 2004.

The project has a total of approximately 255,500 SF new construction with 622 beds in different suites layout with living room and kitchen. The student housing facilities are wood-framed Type V, 1-Hour buildings, three and four stories in height. Generally, they are organized with dwelling units situated along double-loaded corridors served by common elevator/entry lobbies. General study lounges, administrative areas, and service rooms are located adjacent to the elevator lobbies on each floor. The buildings are clad primarily in stucco, and feature both pitched and flat roofs (clad in composite shingles and built-up roofing, respectively).

The one-story commons facility houses a convenience store/cafe' and a multi-purpose meeting room. Classified as Type V, NR building, this one story structure utilizes both steel and wood framing. Befitting its public nature, the building is clad primarily in glass with both stucco and concrete masonry accents. Pitched roofs are standing seam metal, while the built-up flat roof hosts the facility's mechanical equipment.

An expansion to the Phase I project's mechanical plant provides the chilled and hot water for the four pipe mechanical systems that serve the new buildings. Full electrical, plumbing, and life safety systems and telecommunication infrastructure are provided. Site improvements include the courtyard spaces formed by the housing facilities (a combination of planting and hardscape materials), plazas adjacent to the commons facility, a parking lot, and related vehicular and emergency access ways.

Statistical Information

Construction start date:
June 16, 2008
Expected completion date:
Summer 2010
Construction Cost:
$56,329,793
Total Project Cost: $75,778,800
Gross sq. footage:
225,500
Assignable sq. footage:
183,500
% of project complete:
65%

Project Funding

  • Funding for this project is from University Housing Services a department of Student Affairs Division, utilizing a system wide revenue bond with repayment from unit rental income.

Progress of Major Construction Activities

  • Overall site demolition is 94% complete. Framing in Construction Zone 1 & 2 is 95% complete.
  • Underground utility installation at Construction Zone 1 and 2 is 96% complete.
  • Building ‘D’ structural steel erection is complete. Building ‘D’ CMU walls are 90% complete. CMU wall erection is complete at the utility Yard. Color coat is complete on buildings B3, C1 and C2/C3.
  • Building built-up roofing systems project wide are 90% complete. Interior drywall is progressing on buildings B1 and B2/B3. Interior painting and cabinet installation is progressing on buildings C1 and C2/C3.
  • LEED certification meetings have commenced and planning is in progress to certify project.

Key/Critical Issues Currently Pending

  • Implement of Stage 3 construction (Phase III) - On-schedule to begin 8/3/09.

Upcoming Utility or Other Interruptions

  • Impact to electrical services to various buildings due to RS PII electrical connectivity to the campus high voltage grid on Saturday, August 1 through August 2, 2009.

Other Areas of Significance

  • NA at this time.