March 2009 Updates

Residential Suites Phase II

Construction Zone 1 -  Buildings B1 first & second floor framing completed; third floor framing in progress. Click to Zoom. Construction Zone 1 - Buildings B2 & B3 first floor framing and steel erection in progress. Click to Zoom. Construction Zone 1—Building C1 exterior steel stairs, window installation in progress; third floor and roof framing completed. Click to Zoom.
Construction Zone 1 -  Building C2 & C3 floors 1—3 framing        completed; 4th floor, roof & exterior steel stairs framing in progress. Click to Zoom. Construction Zone 1 -	 Building D underground utilities in progress; foundation footings work in progress. Click to Zoom. Construction Zone 2 - Buildings A1 - A3 underground drains & electrical conduits complete; foundation work in progress. Click to Zoom.

About This Project

The Residential Suites Phase II project is a complex of three (3) student housing facilities (Buildings A, B, & C), a commons facility (Building D) and site improvements. This project is located within the boundaries of Kellogg Drive, Eucalyptus Lane, parking lot G, baseball field, Gymnasium Building. It is adjacent to the Residential Suites Phase I, which were constructed in 2004.

The project has a total of approximately 255,500 SF new construction with 622 beds in different suites layout with living room and kitchen. The student housing facilities are wood-framed Type V, 1-Hour buildings, three and four stories in height. Generally, they are organized with dwelling units situated along double-loaded corridors served by common elevator/entry lobbies. General study lounges, administrative areas, and service rooms are located adjacent to the elevator lobbies on each floor. The buildings are clad primarily in stucco, and feature both pitched and flat roofs (clad in composite shingles and built-up roofing, respectively).

The one-story commons facility houses a convenience store/cafe' and a multi-purpose meeting room. Classified as Type V, NR building, this one story structure utilizes both steel and wood framing. Befitting its public nature, the building is clad primarily in glass with both stucco and concrete masonry accents. Pitched roofs are standing seam metal, while the built-up flat roof hosts the facility's mechanical equipment.

An expansion to the Phase I project's mechanical plant provides the chilled and hot water for the four pipe mechanical systems that serve the new buildings. Full electrical, plumbing, and life safety systems and telecommunication infrastructure are provided. Site improvements include the courtyard spaces formed by the housing facilities (a combination of planting and hardscape materials), plazas adjacent to the commons facility, a parking lot, and related vehicular and emergency access ways.

Statistical Information

Construction start date:
June 16, 2008
Expected completion date:
Summer 2010
Construction Cost:
$56,329,793
Total Project Cost: $75,778,800
Gross sq. footage:
225,500
Assignable sq. footage:
183,500
% of project complete:
36%

Project Funding

  • Funding for this project is from University Housing Services a department of Student Affairs Division, utilizing a system wide revenue bond with repayment from unit rental income.

Progress of Major Construction Activities

  • Overall site demolition is 91% complete.
  • Underground utility installation @ Construction Zone #1 is 71% complete.
  • Steel erection at Buildings B1/B2/C1-C3 is in progress. Concrete foundation pads for Buildings in
    Zone 1 are 85% complete. Building D is the last foundation pad to pour.
  • LEED certification meetings have commenced and planning is in progress to certify project.
  • Zone 2 access roads and temporary walkways started. Building A1 foundation pad is poured.

Key/Critical Issues Currently Pending

  • Review of on-going fire access impact @ access road north of Bldgs. #60 & #61.
  • Review/implement impact of Stage 3 construction to Buildings #35, #43, #66 & #55.

Upcoming Utility or Other Interruptions

  • Critical impact dates to Bronco Bookstore and BSC #35 for Eucalyptus Lane closure has been scheduled from 5/27/09 thru 8/1/09.

Other Areas of Significance

  • NA at this time.