Cal Poly Pomona

November 2008 Updates

Residential Suites Phase II

Construction Zone 1  - Building C1 foundation concrete pad; pour completed on 11-5-08. Click to Zoom. Construction Zone 1 - Buildings C2 & C3 foundation rebar      placement and formwork ongoing. Click to Zoom. Construction Zone 1 - Building B1 underground utility work     ongoing; foundation formwork in process. Click to Zoom.
Construction Zone 1 -  Underground electrical and communication conduits. Click to Zoom. Construction Zone 2 -	 Auger grouted placement piles for buildings A1, A2 & A3. Click to Zoom. Construction Zone 2 - Auger grouted placement piles  completed for buildings A1, A2, A3 and building stake-out. Click to Zoom.

About This Project

The Residential Suites Phase II project is a complex of three (3) student housing facilities (Buildings A, B, & C), a commons facility (Building D) and site improvements. This project is located within the boundaries of Kellogg Drive, Eucalyptus Lane, parking lot G, baseball field, Gymnasium Building. It is adjacent to the Residential Suites Phase I, which were constructed in 2004.

The project has a total of approximately 255,500 SF new construction with 622 beds in different suites layout with living room and kitchen. The student housing facilities are wood-framed Type V, 1-Hour buildings, three and four stories in height. Generally, they are organized with dwelling units situated along double-loaded corridors served by common elevator/entry lobbies. General study lounges, administrative areas, and service rooms are located adjacent to the elevator lobbies on each floor. The buildings are clad primarily in stucco, and feature both pitched and flat roofs (clad in composite shingles and built-up roofing, respectively).

The one-story commons facility houses a convenience store/cafe' and a multi-purpose meeting room. Classified as Type V, NR building, this one story structure utilizes both steel and wood framing. Befitting its public nature, the building is clad primarily in glass with both stucco and concrete masonry accents. Pitched roofs are standing seam metal, while the built-up flat roof hosts the facility's mechanical equipment.

An expansion to the Phase I project's mechanical plant provides the chilled and hot water for the four pipe mechanical systems that serve the new buildings. Full electrical, plumbing, and life safety systems and telecommunication infrastructure are provided. Site improvements include the courtyard spaces formed by the housing facilities (a combination of planting and hardscape materials), plazas adjacent to the commons facility, a parking lot, and related vehicular and emergency access ways.

Statistical Information

Construction start date:
June 16, 2008
Expected completion date:
Summer 2010
Construction Cost:
$67,129,000
Total Project Cost: $88,241,000
Gross sq. footage:
225,500
Assignable sq. footage:
183,500
% of project complete:
23%

Progress of Major Construction Activities

  • Overall site demolition is 90% complete.
    Structural production pile installation for Building ‘A’ (Construction Zone #2) was completed on 11/17/08.
  • Under slab utility installation is underway.
  • Underground utility installation @ Construction Zone #1 is 60% complete. Concrete pads for Building ’C’ was completed on 11/25/08. All production piles in this zone are completely installed.

Key/Critical Issues Currently Pending

  • Review of fire access impact @ access road north of Bldg.s #60 & #61 is underway once trenching begins in this area.
  • Review impact of Stage 3 construction to Buildings #35, #43, #66 & #55.

Upcoming Utility or Other Interruptions

  • Local utility impacts to Vista Café and the currently occupied Suites Bldg. #60 & #61 are being reviewed at this time.
  • Coordinate partial closure of the access road off of Kellogg Dr. to allow construction of new parking lot .

Other Areas of Significance

  • NA at this time.