The project is located at Kellogg Drive in between the new residential project and Lot B. It includes the re-construction of an 6” asphalt concrete road and parking spaces as well as tie-in to drainage system located at Kellogg Drive. This site improvements will contribute to better parking and students safety. The total project cost is approximately $150,000 and will be completed by August 2012.
| Construction start date: | June 2012 |
| Expected completion date: | Aug 2012 |
| Construction Cost: | $150,000 |
| Total Project Cost: | $200,000 |
| Gross sq. footage: | 13,250 |
| Assignable sq. footage addition: | 13,250 |
| % of project complete: | 0% |