March 2008 Updates

Lower Reservoir Replacement - Northwest Quadrant

Original damaged main distribution line. Jan. 16, 2008. Click to Zoom. Existing overflow pipe from Upper Reservoir. Jan. 16, 2008. Click to Zoom. Existing 75 hp pump in Equipment House. Jan. 16, 2008. Click to Zoom. Existing Condition of Lower Reservoir Equipment Structure. Click to Zoom.

About This Project

This project scope of work is currently under review. The overall design intent should be finalized within the next few weeks. Primary intent of this project is to improve the campus domestic water system infrastructure.

Statistical Information

Construction start date:
June 2008
Expected completion date:
March 2009
Construction Cost:
TBD
Total Project Cost: $1,515,000
Gross sq. footage:
N/A
Assignable sq. footage:
N/A
% of project complete:
0%

Progress of Major Construction Activities

  • A design consultant has been selected and the design investigation has begun.

Key/Critical Issues Currently Pending

  • Funds for this project are to be encumbered before June 2008.

Upcoming Utility or Other Interruptions

  • TBD

Other Areas of Significance

  • NA at this time.