Lower Reservoir Replacement - Northwest Quadrant

Lower Reservoir at the Northwest Quadrant without previously existing cover. 1-16-2008. Click to Zoom. Floor conditions at existing Reservoir. 1-16-2008. Click to Zoom. Lower Reservoir Equipment Room. 1-16-2008. Click to Zoom. Some electrical devices in the Lower Reservoir Equipment Room. 1-16-2008. Click to Zoom.

About This Project

This project scope of work is currently under review. The overall design intent should be finalized within the next few weeks. Primary intent of this project is to improve the campus domestic water system infrastructure.

Statistical Information

Construction start date:
June 2008
Expected completion date:
March 2009
Construction Cost:
TBD
Total Project Cost: $1,515,000
Gross sq. footage:
N/A
Assignable sq. footage:
N/A
% of project complete:
0%

Progress of Major Construction Activities

  • In preliminary design.

Key/Critical Issues Currently Pending

  • Funds for this project are to be encumbered before June 2008.

Upcoming Utility or Other Interruptions

  • TBD

Other Areas of Significance

  • NA at this time.