About This Project
The project will replace existing deteriorated existing 12” water distribution piping; provides one new 570,000 gallon steel water storage tank with new valves and controls system. Primary intent of this project is to improve the campus domestic water system infrastructure.
Statistical Information
| Construction start date: |
June 2008 |
| Expected completion date: |
Winter 2009 |
| Construction Cost: |
$1,436,500 |
| Total Project Cost: |
$1,515,000 |
| Gross sq. footage: |
N/A |
| Assignable sq. footage: |
N/A |
| % of project complete: |
50% |
Project has been approved to recommence work as of March 2, 2009.
|
Project Funding
- Funding for this project is from the 2007/2008 Capital Renewal Program Funding Source, Proposition 1D (General Obligation Bond).
Progress of Major Construction Activities
- Project has been approved to recommence work as of March 2, 2009.
- The existing water lines at the lower reservoir have been identified and preparations for tie-in are being scheduled.
- The opening required in the existing concrete tank has been completed.
- The tank installation is tentatively scheduled for June 2009.
Key/Critical Issues Currently Pending
- Re-submittal of the tank and foundation design.
- Steel pipe re-submittal.
- Installation of SCADA control system by FM
Upcoming Utility or Other Interruptions
- Steel tank new water lines tie-in, scheduling preparation ongoing with FM and the Contractor.
- Electrical and SCADA system tie-in
- Tank installation and access at Lot A
Other Areas of Significance