August 2008 Updates

Lower Reservoir Replacement - Northwest Quadrant

Original damaged main distribution line. Jan. 16, 2008. Click to Zoom. Existing overflow pipe from Upper Reservoir. Jan. 16, 2008. Click to Zoom. Existing 75 hp pump in Equipment House. Jan. 16, 2008. Click to Zoom.
New access doors rough opening, completed. Click to Zoom. Existing overflow pipe from Upper Reservoir. Jan. 16, 2008. Click to Zoom. Existing 75 hp pump in Equipment House. Jan. 16, 2008. Click to Zoom.

About This Project

The project will replace existing deteriorated existing 12” water distribution piping; provides one new 570,000 gallon steel water storage tank with new valves and controls system. Primary intent of this project is to improve the campus domestic water system infrastructure.

Statistical Information

Construction start date:
June 2008
Expected completion date:
March 2009
Construction Cost:
$1,436,500
Total Project Cost: $1,515,000
Gross sq. footage:
N/A
Assignable sq. footage:
N/A
% of project complete:
25%

Progress of Major Construction Activities

  • Pipe installation from point of connection at Kellogg through Lot C to the Cistern is complete.
  • The impacted landscape areas have been repaired.
  • The tank installation is scheduled for fall 2008.

Key/Critical Issues Currently Pending

  • Re-submittal of the tank design.
  • Installation of SCADA control system by FM

Upcoming Utility or Other Interruptions

  • Water tie-in, scheduled to be completed prior to 9/22/08.
  • Electrical and SCADA system tie-in
  • Tank installation and access at Lot A

Other Areas of Significance

  • NA at this time.