- Planning
- Design & Construction
The project will replace existing deteriorated existing 12” water distribution piping; provides one new 570,000 gallon steel water storage tank with new valves and controls system. Primary intent of this project is to improve the campus domestic water system infrastructure.
| Construction start date: | June 2008
|
| Expected completion date: | March 2009 |
| Construction Cost: | $1,436,500 |
| Total Project Cost: | $1,515,000 |
| Gross sq. footage: | N/A |
| Assignable sq. footage: | N/A |
| % of project complete: | 25% |