August 2011 Updates

Los Olivos Building 70 Refrigeration

Los Olivos Commons-refrigeration rooms located at the kitchen will be replaced during the Summer Quarter calendar. Click to Zoom. New walk-in cooler rooms are installed at Los Olivos. Click to Zoom. Loading Deck will be renewed to comply with Health Department        requirements.  Click to Zoom.
 Loading Deck and parking lot is currently undergoing improvements. Click to Zoom. Mechanical rack will be modernized and transformed into an environmentally friendly unit. Click to Zoom. Newer refrigeration rack will provide better efficiencies and lower energy consumption at Los Olivos. Click to Zoom.

About This Project

The project is located at the Los Olivos Commons Building 70 and includes construction of new kitchen refrigeration rooms on an 1700 SQF area. The new refrigeration rooms will replace existing outdated facilities and include new and efficient mechanical and electrical features. The loading deck and the adjacent parking surface will be replaced with an 8” thick reinforced concrete slab in order to comply with State Health Department requirements. The total project cost is approximately $550,000 and construction will be completed by September 2011.

Statistical Information

Construction start date:
Jun 2011
Expected completion date:
Sep 2011
Construction Cost:
$450,000
Total Project Cost: $550,000
Gross sq. footage:
1750
Assignable sq. footage:
1750
% of project complete:
80%

Project Funding

  • University Housing Services.

Progress of Major Construction Activities

  • The selected refrigeration system uses a more efficient an environmentally friendly approach providing important energy savings.
  • Environmental Abatement and demolition of existing is completed.
  • New walk in refrigeration rooms have been delivered and installed.
  • Mechanical equipment and new electrical and plumbing work is now ongoing.

Key/Critical Issues Currently Pending

  • Fulfillment of fast track construction schedule within remaining 15 days.
  • Rigorous coordination of construction activities with Los Olivos management since dinning services will remain available to students during construction.
  • New mechanical equipment start up and calibration.
  • Completion of new slab on grade and loading deck improvements.

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance

  • NA at this time.