Library Addition and Renovation Phase I

Southeast building corner, landscaping complete. Click to Zoom. South face of Library and Olive Lane, landscaping complete. Click to Zoom. Library main lobby entry, south elevation, landscaping complete. Click to Zoom.

Library main lobby entry, west elevation, landscaping and Olive Lane complete. Click to Zoom. Main Entry Lobby to Library and Academic Lecture Rooms. Click to Zoom. Library Circulation Desk, second floor. Click to Zoom.

About This Project

This project will construct additional library space which will address the need to provide state of the art information stations, library instructional spaces, enhanced reading areas, (including a two-story volume grand reading room), group study rooms, academic lecture spaces as well as 24-hour study space. The existing ground, first and second floors will be remodeled and will include program, accessibility and circulation improvements.

Once the construction portion of the project nears it completion the University will be managing the installation of Group I and II components such as carpeting, book stacks, telephone, data, signage, furniture and equipment required to complete the project. The current budget for this scope of work is 10 million dollars and is scheduled to be completed for the opening of academic classes in fall 2008.

Statistical Information

Construction start date:
Feb 21, 2006
Expected completion date:
Fall 2008
Construction Cost:
$47,875,000
Total Project Cost: $64,200,000
Gross sq. footage:
198,684
Assignable sq. footage (addition):
71,771
Assignable sq. footage (renovation):
78,160
% of project complete:
95%

Progress of Major Construction Activities

  • Major construction complete
  • The Academic Classrooms are complete and available for Fall.
  • Telecom cabling and equipment installation complete.
  • Paging system installation complete.
  • Library shelving installation, 90% complete
  • Flooring installation, 95% complete
  • Interior signage, 65% complete
  • Furniture and Equipment installation, 70% complete

Key/Critical Issues Currently Pending

  • The Starbucks (Library Café) Tenant Improvement project is 60% complete and on schedule to open for Fall quarter.
  • Delivery of the remaining compact shelving units is scheduled for August, 2008.
  • Security Equipment Package 2 (EBP2), has been successfully bid and is scheduled to start in early August and be complete by the end of the year. EBP2 will complete the security system for the Library project.
  • The temporary patron entry has been removed and the main entry has been in use as of June 23.

Upcoming Utility or Other Interruptions

  • N/A at this time

Other Areas of Significance

  • N/A at this time