This project will construct additional library space which will address the need to provide state of the art information stations, library instructional spaces, enhanced reading areas, (including a two-story volume grand reading room), group study rooms, academic lecture spaces as well as 24-hour study space. The existing ground, first and second floors will be remodeled and will include program, accessibility and circulation improvements.
Once the construction portion of the project nears it completion the University will be managing the installation of Group I and II components such as carpeting, book stacks, telephone, data, signage, furniture and equipment required to complete the project. The current budget for this scope of work is 10 million dollars and is scheduled to be completed for the opening of academic classes in fall 2008.
| Construction start date: | Feb 21, 2006 |
| Expected completion date: | Fall 2008 |
| Construction Cost: | $47,875,000 |
| Total Project Cost: | $64,200,000 |
| Gross sq. footage: | 72,323 |
| Assignable sq. footage (addition): | 71,771 |
| Assignable sq. footage (renovation): | 78,160 |
| % of project complete: | 99% |
Deliveries of furniture and equipment scheduled to begin March 2008.
Temporary patron entry has been relocated to the east side of the building and will remain until the installation of telecom, furniture and equipment is completed for the fall 2008 opening.