September 2007 Updates

Library Addition and Renovation Phase I

About This Project

This project will construct additional library space which will address the need to provide state of the art information stations, library instructional spaces, enhanced reading areas, (including a two-story volume grand reading room), group study rooms, academic lecture spaces as well as 24-hour study space. The existing ground, first and second floors will be remodeled and will include program, accessibility and circulation improvements.

Once the construction portion of the project nears it completion the University will be managing the installation of Group I and II components such as carpeting, book stacks, telephone, data, signage, furniture and equipment required to complete the project. The current budget for this scope of work is 10 million dollars and is scheduled to be completed for the opening of academic classes in fall 2008.

Statistical Information

Construction start date:
Feb 21, 2006
Expected completion date:
March 2008
Construction Cost:
$47,875,000
Total Project Cost: $64,200,000
Gross sq. footage (renovation):
96,831
Gross sq. footage (addition):
101,853
Assignable sq. footage (renovation):
78,160
Assignable sq. footage (addition):
71,771
% of project complete:
93%

Progress of Major Construction Activities

  • Exterior mullions and glazing at addition, complete
  • Underground hot and chilled water piping mains installation, complete
  • Re-roofing of Building 16 (roundhouse) underway, 70% complete
  • Emergency Generator installation underway, complete

Key/Critical Issues Currently Pending

  • NA at this time

Two-Week Look Ahead of Major Activities

  • Site work at north area underway, complete
  • Olive Lane Improvements Map area Part C underway, complete
  • Installation of new elevators underway, 75% complete\
  • Fire alarm installation at existing building underway, 90% complete
  • Repainting of existing Library to begin.

Upcoming Utility or Other Interruptions

  • N/A at this time

Other Areas of Significance

  • Temporary patron entry has been relocated to the east side of the building in order for temporary entry tunnel on west side to be removed.
  • The quantity of sub-contractors on site is anticipated to increase significantly over the next few months as work progresses in both the existing building and the new addition.