I Poly High School

Site Plan. Click to Zoom. Perspective showing courtyard. Click to Zoom. Structural steel erection at Building A. Click to Zoom.
Concrete being pumped into the footing of Bldg. Click to Zoom. installing the 18' deep sleeve for the elevator shaft of Building B. Click to Zoom. Temple Av access-Concrete and curb gutter being installed. Click to Zoom.

About This Project

Through a lease agreement between Cal Poly Pomona and Los Angeles County Office of Education (LACOE), the International Polytechnic High School (I-Poly) will be constructed in the south quadrant of the campus, adjacent to the University athletic fields to the north and Temple Avenue to the south. This project will construct permanent facilities for I-Poly, including associated site-work. The new 52,000 GSF facility will house grades 9-12 in a two-story structure and includes classrooms, science lab, administrative offices, multi-purpose room, outdoor learning spaces and miscellaneous ancillary spaces.

The site for the new facility is approximately two acres and consists of general site improvements with landscape, courtyard, hardscape and reconfigured parking spaces. Planned off-site project improvements will include two new vehicular parking lot entrances, reconfiguration to existing parking lots, creation of a new green space pedestrian connection to the University and athletic facilities.

LACOE will manage the design and construction of this entire project. Cal Poly Pomona, through an approved Operating Agreement, will provide general campus oversight. Student occupancy is tentatively scheduled for Sep 2012.

Statistical Information

Construction start date:
Feb 2011
Expected completion date:
May 2012
Construction Cost:
$17,000,000
Total Project Cost: $22,000,000
Gross sq. footage:
44,579
Assignable sq. footage:
42,175
% of project complete:
14%

Project Funding

  • Los Angeles County Office of Education utilizing Proposition ID (General Obligation Bond) Funds.
    Funding has been approved by the State Allocation Board and the Office of Public School Construction.

Progress of Major Construction Activities

  • Form/Pour New Offsite street concrete scheduled to complete on July 29th.
  • Structural Steel for Building A started on July 26th.
  • Building B footings are scheduled to be completed by July 29th.

Key/Critical Issues Currently Pending

  • NA

Upcoming Utility or Other Interruptions

  • NA

Other Areas of Significance

  • NA at this time.