Contents
Cal Poly Pomona

June 2011 Updates

Innovation Village Ph. IV

View of the front of the building looking north (6/29/11). Click to Zoom. 2nd Floor open and closed office space  with ceiling grid. (6/9/11). Click to Zoom. Working the roof top solar panel installation (5/24/11).  Click to Zoom.
3rd Floor Office build out. (6/9/11). Click to Zoom. Solar PV mounting system being installed on the roof. (6/9/11). Click to Zoom. Solar Inverter installation at roof (5/11/11). Click to Zoom.

About This Project

Construction of a new 123,060 SF concrete tilt-up office facility on a 6.7 acre Innovation Village Research Park site. The new three story structure is the second of several facilities master planned for the Research Park to partner with organizations which are aligned with the mission of the University and will promote partnerships within the University’s academic environment as well as provide jobs and economic growth to our surrounding community. This facility is being constructed for the exclusive use by Southern California Edison and is their second facility in the park. Trammell Crow Company in a joint venture with Millie Severson Inc. are the contractor for the facility and the site improvements including the second phase of the Innovation Way extension. Also included in the project will be LEED Gold measures, a new bio-swale storm water drainage system, and site improvements matching those completed in the Phase III site.

Statistical Information

Construction start date:
Dec 2009
Expected completion date:
June 2011
Construction Cost:
$21,323,000
Total Project Cost:
$27,929,000
Gross sq. footage:
123,060
Assignable sq. footage:
110,500
% of project complete:
95%

Project Funding

  • Cal Poly Pomona Foundation Inc.

Progress of Major Construction Activities

  • HVA/C duct work and insulation.
  • Completion site landscape irrigation systems.
  • Installation of plumbing and electrical interior rough-ins
  • Installation of fire sprinkler drops and heads
  • Interior Tenant space walls
  • Finish work within the restrooms
  • Roof top solar panel support system
  • Landscape plantings

Key/Critical Issues Currently Pending

  • NA at this time.

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance

  • NA at this time.