Concrete infill at first floor column bases (9/28/10). Click to Zoom. New concrete drive entry off of Innovation Way for Phase IV and CTTi (9/28/10). Click to Zoom. View from third floor looking southwest, parking lot in foreground with CTTi and Amonix Solar Array in background (9/28/10). click to Zoom.

About This Project

Construction of a new 123,060 SF concrete tilt-up office facility on a 6.7 acre Innovation Village Research Park site. The new three story structure is the second of several facilities master planned for the Research Park to partner with organizations which are aligned with the mission of the University and will promote partnerships within the University’s academic environment as well as provide jobs and economic growth to our surrounding community. This facility is being constructed for the exclusive use by Southern California Edison and is their second facility in the park. Trammell Crow Company in a joint venture with Millie Severson Inc. are the contractor for the facility and the site improvements including the second phase of the Innovation Way extension. Also included in the project will be LEED Gold measures, a new bio-swale storm water drainage system, and site improvements matching those completed in the Phase III site.

Statistical Information

Construction start date:
Dec 2009
Expected completion date:
June 2011
Construction Cost:
$21,323,000
Total Project Cost:
$27,929,000
Gross sq. footage:
123,060
Assignable sq. footage:
110,500
% of project complete:
56%

Project Funding

  • Cal Poly Pomona Foundation Inc.

Progress of Major Construction Activities

  • Completion of Monokote Fireproofing.
  • Start of interior core wall framing.
  • Start of HVA/C duct work.
  • Installation of roof top HVA/C Units.
  • Completion of roofing insulation and roof membrane.
  • Installation of miscellaneous steel work around the buildings perimeter.
  • Prep of Innovation Way II for asphalt.

Key/Critical Issues Currently Pending

  • NA at this time.

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance