Contents
Cal Poly Pomona

July 2010 Updates

Innovation Village Ph. IV

Rendering of Innovation Village Phase IV. Click to Zoom. Installation of structural steel within the building  (7/08/10). Click to Zoom. Installation of structural steel within the building  (7/08/10).  Click to Zoom.
Installation of structural steel within the building  (7/08/10).  Click to Zoom. Installation of structural steel within the building  (7/08/10). Click to Zoom. Installation of structural steel within the building  (7/08/10). click to Zoom.

About This Project

Construct a new 123,060 square foot concrete tilt-up office facility on a 6.7 acre Innovation Village Research Park site. The new three story structure is the second of several facilities master planned for the Research Park to partner with organizations which are aligned with the mission of the University and will promote partnerships within the university’s academic environment as well as provide jobs and economic grow to our surrounding community. This facility is being constructed for the exclusive use by Southern California Edison and is their second facility in the park. Trammell Crow Company in a joint venture with Millie Severson Inc. are the contractor for the facility and the site improvements including the second phase of the Innovation Way extension. Also included in the project will be LEED Gold measures, a new bio-swale storm water drainage system, and site improvements matching those completed in the Phase III site.

Statistical Information

Construction start date:
Dec 2009
Expected completion date:
June 2010
Construction Cost:
$21,323,000
Total Project Cost:
$27,929,000
Gross sq. footage:
123,060
Assignable sq. footage:
110,500
% of project complete:
35%

Project Funding

  • Funding for this project is through Cal Poly Pomona Foundation Inc.

Progress of Major Construction Activities

  • Installation of structural steel
  • Installation of main utility feeds in Innovation Way
  • Layout of parking area curbs and gutters

Key/Critical Issues Currently Pending

  • NA at this time.

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance

  • NA at this time.