August 2010 Updates

Innovation Landscape Ph. II

New sign at Temple and Valley (8/12/10). Click to Zoom. New landscaping at Temple and Valley (8/12/10). Click to Zoom. Forming the sign stem wall for Temple and Valley (8/12/10). Click to Zoom.
Sign atop stem wall  with foundations fro circular site walls at Temple and Valley (8/17/10).  Click to Zoom. Replacement sidewalks along Temple Ave,  (8/17/10). Click to Zoom. Cal Poly Pomona Sign at Temple and Valley with site walls (8/26/10).  click to Zoom.

About This Project

Construct new sidewalks, marquee signage, walkway lights, street lights and landscaping along the entire face of the Innovation Village’s eastern side (Valley Blvd.) and southern side (Temple Ave.) including the reconfiguration of the CTTi entry to align for the future connection of Innovation Way, which will be providing a secondary entry into the Innovation Village Research and Development Park. The signage package for this project will create new updated entrance signs into the park as well as create a new and exciting gateway entrance to our wonderful campus. The project is a collaboration with the Federal Economic Development Agency (EDA) and Cal Poly Pomona Foundation, Inc. and is the last of six projects partial funded under this latest grant from EDA. Belaire–West Landscaping, Inc, a local contractor is on a very tight schedule to complete the entire project by mid summer.

Statistical Information

Construction start date:
Apr 2010
Expected completion date:
July 2010
Construction Cost:
$1,070,000
Total Project Cost:
$1,438,000
Gross sq. footage:
NA
Assignable sq. footage:
NA
% of project complete:
99%

Project Funding

  • Cal Poly Pomona Foundation Inc. and EDA

Progress of Major Construction Activities

  • Installation of bollard lights
  • Installation of the two large signs and landscaping
  • Installation of the landscape light fixtures
  • Installation of the irrigation water meters
  • Installation of the balance of the plants and groundcover.

Key/Critical Issues Currently Pending

  • Re-fabrication of the four small signs
  • Electrical feeder installation and SCE approvals

Upcoming Utility or Other Interruptions

  • NA at this time

Other Areas of Significance

  • NA at this time.