Landscaping and sign foundation at Innovation Way & Temple Ave. (7/27/10). Click to Zoom. Adjusting the irrigation sprinklers at the new landscaping at CTTi Complex (7/27/10). Click to Zoom. New concrete cross-gutter and asphalt intersection at Innovation Way and Temple Ave (7/19/10).  Click to Zoom.
Preparing the newly created corner at Innovation Way and Temple Ave. for landscaping. (7/19/10).  Click to Zoom. Sign foundation work at Kellogg Dr. and Valley Blvd  (7/22/10). Click to Zoom. Sign foundation work at Innovation Way and Temple Ave. (7/22/10).  click to Zoom.

About This Project

Construct new sidewalks, marquee signage, walkway lights, street lights and landscaping along the entire face of the Innovation Village’s eastern side (Valley Blvd.) and southern side (Temple Ave.) including the reconfiguration of the CTTi entry to align for the future connection of Innovation Way, which will be providing a secondary entry into the Innovation Village Research and Development Park. The signage package for this project will create new updated entrance signs into the park as well as create a new and exciting gateway entrance to our wonderful campus. The project is a collaboration with the Federal Economic Development Agency (EDA) and Cal Poly Pomona Foundation, Inc. and is the last of six projects partial funded under this latest grant from EDA. Belaire–West Landscaping, Inc, a local contractor is on a very tight schedule to complete the entire project by mid summer.

Statistical Information

Construction start date:
Apr 2010
Expected completion date:
July 2010
Construction Cost:
$1,070,000
Total Project Cost:
$1,438,000
Gross sq. footage:
NA
Assignable sq. footage:
NA
% of project complete:
89%

Project Funding

  • Cal Poly Pomona Foundation Inc. and EDA

Progress of Major Construction Activities

  • Installation of trees and shrubs.
  • Installation of street lights.
  • Installation of sign foundations.
  • Installation of cross gutter and asphalt at Innovation Way and Temple
  • Relocation of 8” water main back-flow/meter device.
  • Removal of the water main at Innovation Way and Temple

Key/Critical Issues Currently Pending

  • Light fixture delivery
  • Electrical feeder installation and SCE approvals

Upcoming Utility or Other Interruptions

  • NA at this time

Other Areas of Significance

  • NA at this time.