Planting of new trees at the Kellogg Dr. / Valley Blvd. southwest corner (6/15/10). Click to Zoom. Planting of new trees at the Kellogg Dr. / Valley Blvd. northwest corner (6/15/10). Click to Zoom. New trees and shrubs along Valley Blvd. north of Kellogg Dr. (6/15/10).  Click to Zoom.
Preparing to place new tree (6/15/10).  Click to Zoom. Work on the new Innovation Way/Temple Ave intersection next to the CTTi complex. (6/15/10). Click to Zoom. New trees and shrubs along Valley Blvd. (6/15/10).  click to Zoom.

About This Project

Construct new sidewalks, marquee signage, walkway lights, street lights and landscaping along the entire face of the Innovation Village’s eastern side (Valley Blvd.) and southern side (Temple Ave.) including the reconfiguration of the CTTi entry to align for the future connection of Innovation Way, which will be providing a secondary entry into the Innovation Village Research and Development Park. The signage package for this project will create new updated entrance signs into the park as well as create a new and exciting gateway entrance to our wonderful campus. The project is a collaboration with the Federal Economic Development Agency (EDA) and Cal Poly Pomona Foundation, Inc. and is the last of six projects partial funded under this latest grant from EDA. Belaire–West Landscaping, Inc, a local contractor is on a very tight schedule to complete the entire project by mid summer.

Statistical Information

Construction start date:
Apr 2010
Expected completion date:
July 2010
Construction Cost:
$1,070,000
Total Project Cost:
$1,438,000
Gross sq. footage:
NA
Assignable sq. footage:
NA
% of project complete:
65%

Project Funding

  • Cal Poly Pomona Foundation Inc. and EDA

Progress of Major Construction Activities

  • Installation of trees and shrubs.
  • Installation of irrigation heads and controls.
  • Installation of walkway light based.
  • Installation of sign foundations.
  • Installation of seating area site wall at CTTi.
  • Relocation of 8” water main back-flow/meter device.

Key/Critical Issues Currently Pending

  • Light fixture delivery
  • Electrical feeder installation and SCE approvals

Upcoming Utility or Other Interruptions

  • NA at this time

Other Areas of Significance

  • NA at this time.