Construct new sidewalks, marquee signage, walkway lights, street lights and landscaping along the entire face of the Innovation Village’s eastern side (Valley Blvd.) and southern side (Temple Ave.) including the reconfiguration of the CTTi entry to align for the future connection of Innovation Way, which will be providing a secondary entry into the Innovation Village Research and Development Park. The signage package for this project will create new updated entrance signs into the park as well as create a new and exciting gateway entrance to our wonderful campus. The project is a collaboration with the Federal Economic Development Agency (EDA) and Cal Poly Pomona Foundation, Inc. and is the last of six projects partial funded under this latest grant from EDA. Belaire–West Landscaping, Inc, a local contractor is on a very tight schedule to complete the entire project by mid summer.

Statistical Information

Construction start date:
Apr 2010
Expected completion date:
July 2010
Construction Cost:
$1,070,000
Total Project Cost:
$1,438,000
Gross sq. footage:
NA
Assignable sq. footage:
NA
% of project complete:
15%

Project Funding

  • Funding for this project is through Cal Poly Pomona Foundation Inc.

Progress of Major Construction Activities

  • Installation of concrete walkways along Valley Blvd.
  • Installation of the new irrigation water main line.
  • Installation of underground electrical conduits for walkway lights.
  • Tree selection

Key/Critical Issues Currently Pending

  • Plant Material Submittals
  • City of Pomona Water Approvals

Upcoming Utility or Other Interruptions

  • NA at this time

Other Areas of Significance

  • NA at this time.