Cal Poly Pomona

February 2011 Updates

Fire Lane to NE Quadrant

Existing concrete road will be continued towards the CBA and Parking lot H. Click to Zoom. View of new Fire Lane extension and new swales. Click to Zoom. Contractor setting  construction fences at the Parking Lot H site.  Click to Zoom.
Compaction of sub base prior to new concrete slab at parking lot. Click to Zoom. Parking Lot H improvements: Relocation of existing light fixtures.  Click to Zoom. Temporary detour pathways will be installed. Students traffic will be routed to Olive Lane  during implementation of Parking  lot. Click to Zoom.

About This Project

The project is located near the Rose Garden, the CLA building and Red Gum. It includes the construction of an 8” thick reinforced concrete fire lane (phase I completed) and renovation of an ADA parking lot located between Red Gum and the College of Business. This site improvements will contribute to safety and ADA compliance on Campus. The total project cost is approximately $450,000 and will be completed by June 2011.

Statistical Information

Construction start date:
Jan 2010
Expected completion date:
June 2011
Construction Cost:
$350,000
Total Project Cost:
$450,000
Gross sq. footage:
16,250
Assignable sq. footage:
NA
% of project complete:
80%

Project Funding

  • Vote approved General Obligation Bonds.

Progress of Major Construction Activities

  • Construction of ADA improvements at Parking Lot H has started on February 1.
  • Detour signs by CLA building and Red Gum are now in place. Construction fences were installed at the site.
  • Contractor has completed the Fire Lane road activities (Phase I) including installation of new drainage and underground electrical infrastructure.
  • Project funds were successfully extended to June of 2011 allowing for additional improvements on Campus of parking lot and additional ADA upgrades.
  • Compaction of sub base soils to a 95% degree was achieved.
  • Electric vehicles belonging to the Students affairs division have been temporarily relocated to improve safety.

Key/Critical Issues Currently Pending

  • Timely implementation of parking lot improvements at parking Lot H and use of all available funds prior to expiration in June 2011.
  • Assure safety and continuous coordination of detour pathways to students and staff during parking lot construction activities.

Upcoming Utility or Other Interruptions

  • NA at this time

Other Areas of Significance

  • NA at this time.