October 2010 Updates

Fire Lane to NE Quadrant

Existing concrete road will be continued towards the CBA and Parking lot H. Click to Zoom. View of new Fire Lane extension and new swales. Click to Zoom. Parking lot improvements will include upgrading of open swales and  to storm drain system.  Click to Zoom.
Opening of Fire Lane  Phase I. Preservation of  two major Jacaranda trees was successfully  achieved.   Click to Zoom. Existing gate and fence  will be removed at Parking lot H allowing additional staff and DSA parking spots at this location.  Click to Zoom. Temporary detour pathways will be installed. Students traffic will be routed to Olive Lane  during implementation of Parking  lot. Click to Zoom.

About This Project

The project is located near the Rose Garden, the CLA building and Red Gum. It includes the construction of an 8” thick reinforced concrete fire lane (phase I completed) and renovation of an ADA parking lot located between Red Gum and the College of Business. This site improvements will contribute to safety and ADA compliance on Campus. The total project cost is approximately $450,000 and will be completed by June 2011.

Statistical Information

Construction start date:
Jan 2010
Expected completion date:
June 2011
Construction Cost:
$350,000
Total Project Cost:
$450,000
Gross sq. footage:
16,250
Assignable sq. footage:
NA
% of project complete:
75%

Project Funding

  • Vote approved General Obligation Bonds.

Progress of Major Construction Activities

  • Contractor has completed the Fire Lane road activities (Phase I) including installation of new drainage and underground electrical infrastructure.
  • Project funds were successfully extended to June of 2011 allowing for additional improvements on Campus.

Key/Critical Issues Currently Pending

  • Review of existing parking Lot H design, and accommodate current elevations and site conditions for proper functioning and ADA compliance.
  • Implement Parking lot improvements at parking Lot H located between Red Gum and College of Business Administration.
  • Coordinate detour pathways to students and staff during parking lot construction activities.

Upcoming Utility or Other Interruptions

  • NA at this time

Other Areas of Significance

  • NA at this time.