Contents
Cal Poly Pomona

April 2010 Updates

Fire Lane to NE Quadrant

Existing concrete road will be continued towards the CBA and Parking lot H. Click to Zoom. Existing underground electrical utilities were identified and located at the road. New  lighting infrastructure is being installed.  Click to Zoom. View of Fire Lane road excavation at the Rose Garden location. Click to Zoom.
Cutting of control joints intended to avoid cracking of newly finished  concrete surfaces.  Click to Zoom. View of new Fire Lane extension and new swales. Click to Zoom. Group of students using detour pathways at the Fire Lane site.  Click to Zoom.

About This Project

The project is located near the Rose Garden, the CLA building and the southeast corner of the College of Business project site. It includes the construction of an 8” thick reinforced concrete Fire Lane and ADA Pathway road. The 650-feet long by 25-feet wide pathway will connect Lot H, which will be upgraded with Accessible parking spaces, and the existing pathway next to the CLA building. The total project cost is approximately $395,000 and will be implemented during the first half of 2010.

Statistical Information

Construction start date:
Jan 2010
Expected completion date:
May 2010
Construction Cost:
$350,000
Total Project Cost:
$450,000
Gross sq. footage:
16,250
Assignable sq. footage:
NA
% of project complete:
60%

Project Funding

  • Vote approved General Obligation Bonds.

Progress of Major Construction Activities

  • Contractor has completed road concrete activities, open swales and installation of underground electrical infrastructure.
  • Sources of surface runoff water were identified to properly install the new storm drain system.
  • Possibly impact to two existing Jacaranda trees has been identified and eliminated.

Key/Critical Issues Currently Pending

  • Complete underground storm drain activities at Olive Lane and towards the CBA site.
  • Assure project funds are extended beyond June 30, 2010 in order to allow full completion of the scope of work, particularly the Phase II road sections located within the College of Business site and at parking lot H.
  • Complete the ADA walkways between parking lot H and the new Fire Lane road.
  • Coordinate campus events scheduled for the upcoming weeks and months and located within the proximities of the Fire Lane road site.
  • Coordinate complete site safety at this crowded students location and provide alternative routes for pedestrians.

Upcoming Utility or Other Interruptions

  • NA at this time

Other Areas of Significance

  • NA at this time.