December 2009 Updates

Fire Lane to NE Quadrant

View of the Rose Garden location where the new Fire Lane project is  implemented.  Click to Zoom. Existing sidewalks will be modified. The new Fire Lane to the CBA will  improve Campus pedestrian and vehicular pathways. Click to Zoom. Stakes showing the road alignment  were established by the project surveyor.  Click to Zoom.
Existing concrete road will be continued towards the CBA and Parking lot H. Click to Zoom. Existing drain storm  to collect surface runoff water from the Rose Garden and the Fire Lane drainage basins. Click to Zoom. Existing locations surrounding the Rose Garden and the CLA building will be fenced up during construction. Click to Zoom.

About This Project

The project is located near the Rose Garden, the CLA building and the southeast corner of the College of Business project site. It includes the construction of an 8” thick reinforced concrete Fire Lane and ADA Pathway road. The 650-feet long by 25-feet wide pathway will connect Lot H, which will be upgraded with Accessible parking spaces, and the existing pathway next to the CLA building. The total project cost is approximately $395,000 and will be implemented during the first half of 2010.

Statistical Information

Construction start date:
Jan 2010
Expected completion date:
May 2010
Construction Cost:
$295,000
Total Project Cost:
$395,000
Gross sq. footage:
16,250
Assignable sq. footage:
NA
% of project complete:
10%

Project Funding

  • Funding for this project is from Minor Caps funding

Progress of Major Construction Activities

  • Notice to Proceed to EPS has been issued by the Procurement Office.
  • Contractor has stake out the new fire lane at the Rose garden proximities,
  • Sources of surface runoff water were identified to properly design the storm drain system.
  • Possibly impact to existing Jacaranda trees has been identified at the site and steps taken to reduce impact.

Key/Critical Issues Currently Pending

  • Minimize impact to Rose garden landscape, trees and infrastructure by means of road repositioning.
  • Coordinate storm drain design issues at the site.
  • Fence up the construction site and install temporary signage and walkways for pedestrians.

Upcoming Utility or Other Interruptions

  • NA at this time

Other Areas of Significance

  • NA at this time.