About This Project

The project will extend existing electrical and telecom infrastructure near the Rose Garden and CLA building into the northeast quadrant of the campus necessary for future development. The new electrical infrastructure consists of three 5” power conduits and three manholes. The new telecom infrastructure will connect existing manhole #71 towards the northwest corner of the new College of Business site. Implementation of the infrastructure work is now 75% completed and is expected to be completed by November 2009. The total project cost is approximately $310,000.The project is currently in progress and the pace of work was significantly increased before commencing of the Spring Quarter in order to minimize possible impacts in and around the CLA building.

Statistical Information

Construction start date:
Aug 2009
Expected completion date:
Nov 2009
Construction Cost:
$220,000
Total Project Cost:
$310,000
Gross sq. footage:
2100
Assignable sq. footage:
1400
% of project complete:
95%

Project Funding

  • Funding for this project is from Minor Caps funding

Progress of Major Construction Activities

  • Electrical infrastructure has been excavated and three (3) underground conduits installed
  • Telecom infrastructure has been excavated and four (4) underground conduits installed.
  • Concrete encasement has been set at both trenches.
  • Electrical and telecom vaults were installed
  • Concrete was repaired at the north entrances of the CLA building.
  • Landscape spaces are being restored at the Rose Garden.

Key/Critical Issues Currently Pending

  • Assure landscape spaces are restored to previous conditions.

Upcoming Utility or Other Interruptions

  • NA at this time

Other Areas of Significance

  • NA at this time.