Contents
Cal Poly Pomona

September 2009 Updates

Electrical and Telecom to NE Quadrant

Excavation of the Telecom  infrastructure at the Rose Garden place. Click to Zoom. View of  Telecom  infrastructure plan for the CBA project.  Click to Zoom. Typical pipe installation before encasement. Click to Zoom.
At CLA north entrance typical setting of pipe trajectory before Concrete is removed. Click to Zoom. Protecting fencing and concrete removal  at CLA before the  start of Spring Quarter. Click to Zoom. Setting of Telecom Vault at the College of Business site. Click to Zoom.

About This Project

The project will extend existing electrical and telecom infrastructure near the Rose Garden and CLA building into the northeast quadrant of the campus necessary for future development. The new electrical infrastructure consists of three 5” power conduits and three manholes. The new telecom infrastructure will connect existing manhole #71 towards the northwest corner of the new College of Business site. Implementation of the infrastructure work is now 75% completed and is expected to be completed by November 2009. The total project cost is approximately $310,000.The project is currently in progress and the pace of work was significantly increased before commencing of the Spring Quarter in order to minimize possible impacts in and around the CLA building.

Statistical Information

Construction start date:
Aug 2009
Expected completion date:
Nov 2009
Construction Cost:
$220,000
Total Project Cost:
$310,000
Gross sq. footage:
2100
Assignable sq. footage:
1400
% of project complete:
75%

Project Funding

  • Funding for this project is from Minor Caps funding

Progress of Major Construction Activities

  • Electrical infrastructure has been excavated and three (3) underground conduits installed
  • Telecom infrastructure has been excavated and four (4) underground conduits installed.
  • Concrete encasement has been set at both trenches.
    Electrical and telecom vaults were installed.

Key/Critical Issues Currently Pending

  • Assure landscape spaces are restored to previous conditions.
  • Assure campus students and staff are minimally impacted by construction site activities.

Upcoming Utility or Other Interruptions

  • NA at this time

Other Areas of Significance

  • NA at this time.