Domestic Water Line Loop Extension Ph. II & IIA

Existing fences on top of the concrete walls were   replaced at the channel crossing. Click to Zoom. Landscape has been restored at the CTTI parking lot. Click to Zoom. New tree planted at the west side of the San Jose creek channel crossing. Click to Zoom.
New fire hydrant at the Temple Av. South Campus Drive intersection is ready for inspection. Click to Zoom. A new fire hydrant was installed at the end of South Campus Drive near the Agriscapes/Farmstore. Click to Zoom. Temporary end cap for chlorination and testing; final point of connection to be coordinated with Innovation Village Phase  4. Click to Zoom.

About This Project

The project consists of a new 10” water line connecting the two existing ends of the campus’ domestic water service, including fire hydrants and flood control channel crossings.

Statistical Information

Construction start date:
July 2008
Expected completion date:
Nov 2008
Construction Cost:
$146,390
Total Project Cost: $342,000
Gross sq. footage:
N/A
Assignable sq. footage Addition:
N/A
% of project complete:
85%

Progress of Major Construction Activities

  • The 10” pipe has been installed along the Agriscapes field north of South Campus Drive, across the San Jose Creek channel, and along the Center for Training Technology & Incubation parking lot. Pipe Installation will continue to a final point of connection by Innovation Way.

Key/Critical Issues Currently Pending

  • Contractor has been directed to chlorinate, disinfect and pressure test the line at a point near the east end of the CTTI parking lot; remaining installation of the 10” pipe will be phased and coordinated with the work (by others) of Innovation Village Phase 4 building site and structure.

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance

  • NA at this time.