About This Project
The project consists of a new 10” water line connecting the two existing ends of the campus’ domestic water service, including fire hydrants and flood control channel crossings.
Statistical Information
| Construction start date: |
July 2008
|
| Expected completion date: |
Nov 2008 |
| Construction Cost: |
$146,390 |
| Total Project Cost: |
$342,000 |
| Gross sq. footage: |
N/A |
| Assignable sq. footage Addition: |
N/A |
| % of project complete: |
70% |
Progress of Major Construction Activities
- The 10” pipe has been installed along the Agriscapes field north of South Campus Drive, across the San Jose Creek channel, and along the Center for Training Technology & Incubation parking lot. Pipe Installation will continue to a final point of connection by Innovation Way.
Key/Critical Issues Currently Pending
- Completion of this work will be phased and coordinated with the work (by others) of Innovation Village Phase 4 building site and structure.
Upcoming Utility or Other Interruptions
Other Areas of Significance