Contents
Cal Poly Pomona

July 2008 Updates

Domestic Water Line Loop Extension Ph. II & IIA

Trenching for the new water pipe along Agriscapes field. Click to Zoom. Contractor is connecting sections of the 10” pipe. Click to Zoom. A future branch connection on the main run of pipe. Click to Zoom. A section of the new 10” pipe is being lowered into the 5 ft  deep trench. Click to Zoom.

About This Project

The project consists of a new 10” water line connecting the two existing ends of the campus’ domestic water service, including fire hydrants and flood control channel crossings.

Statistical Information

Construction start date:
July 2008
Expected completion date:
Nov 2008
Construction Cost:
$146,390
Total Project Cost: $342,000
Gross sq. footage:
N/A
% of project complete:
5%

Progress of Major Construction Activities

  • The first sections of pipe are being installed along the Agriscapes field north of South Campus Drive, the pipe will be routed on the street across building 211 to a point of connection west of the building.

Key/Critical Issues Currently Pending

  • NA at this time.

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance

  • NA at this time.