About This Project

The CTTI Wet Lab Phase II project is located at the intersection of Temple Ave. and South Campus Drive, at the Center for Training Technology & Incubation. The Wet Labs Phase II Project will add 4,500 SF of custom built additional area, intended to meet the most stringent industry standards.

The construction documents phase of the project is currently been completed; the estimated total project cost is $950,000 dollars. Half of these funds are funded by federal funds, through the Economic Development Agency (EDA) and the other half by the Cal Poly Pomona Foundation. The finished building will be leased for commercial and industry use only, and is expected to be available in 2009.

Statistical Information

Construction start date:
April 2009
Expected completion date:
Sept. 2009
Construction Cost:
$400,000
Equipment $83,000
Total Project Cost: $650,000
Gross sq. footage:
4500
Assignable sq. footage:
3850
% of project complete:
50%

Project Funding

  • Funding for this project is from Cal Poly Pomona Foundation Inc. and a matching grant from the Federal Economic Development Administration.

Progress of Major Construction Activities

  • Rough electrical and HVAC at drywalls and ceilings have been installed.
  • Rough plumbing has been completed and is ready to receive the lab equipment.
  • Curbs and steel frames have been lifted to the roof.
  • Fire alarm submittals have been approved.

Key/Critical Issues Currently Pending

  • Install two new HVAC units at the roof.
  • Assure adequate waterproofing is carried out in order to preserve the manufacturer’s warranty.
  • Complete repair of existing cracks and install new flooring.
  • The Lab’s furniture and equipment will be installed during the month of July 2009.

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance

  • NA at this time.