May 2009 Updates

CTTI Wet Labs - Phase II

CTTI Building. Click to Zoom. . An independent HVAC system is currently being installed at each Wet Lab.  Click to Zoom.
Parking lot and truncated domes will me modified to accommodate for recent DSA requirements. Click to Zoom. Work progress showing  new partition walls at the site. Click to Zoom. Location shown is intended for  Wet Lab equipment. Click to Zoom.

About This Project

The CTTI Wet Lab Phase II project is located at the intersection of Temple Ave. and South Campus Drive, at the Center for Training Technology & Incubation. The Wet Labs Phase II Project will add 4,500 SF of custom built additional area, intended to meet the most stringent industry standards.

The construction documents phase of the project is currently been completed; the estimated total project cost is $950,000 dollars. Half of these funds are funded by federal funds, through the Economic Development Agency (EDA) and the other half by the Cal Poly Pomona Foundation. The finished building will be leased for commercial and industry use only, and is expected to be available in 2009.

Statistical Information

Construction start date:
April 2009
Expected completion date:
Sept. 2009
Construction Cost:
$400,000
Equipment $83,000
Total Project Cost: $650,000
Gross sq. footage:
4500
Assignable sq. footage:
3850
% of project complete:
30%

Project Funding

  • Funding for this project is from Cal Poly Pomona Foundation Inc. and a matching grant from the Federal Economic Development Administration.

Progress of Major Construction Activities

  • Construction has started on April 20 and site activities are proceeding according to plan
  • The Lab’s furniture and equipment submittals have been reviewed by the Owner.
  • Rough electrical, plumbing and HVAC at drywalls and ceilings have been installed.
  • Fire alarm submittals are currently under review.
  • Weekly meetings are being conducted at the site including CPPF, FD&C and Contractor.

Key/Critical Issues Currently Pending

  • Contractor to finalize submittal of the Schedule of Values and Project Schedule for approval of payment application.
  • Architect to complete review of paint submittals and ventilation of specialized furniture equipment.

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance

  • NA at this time.