Contents
Cal Poly Pomona

April 2009 Updates

CTTI Wet Labs - Phase II

CTTI Building. Click to Zoom. . View of proposed office space for Wet Lab. Click to Zoom.
Parking lot and truncated domes will me modified to accommodate for recent DSA requirements. Click to Zoom. An independent HVAC system is currently being installed at each Wet Lab.  Click to Zoom. New stud frames and electrical infrastructure at the site. Click to Zoom.

About This Project

The CTTI Wet Lab Phase II project is located at the intersection of Temple Ave. and South Campus Drive, at the Center for Training Technology & Incubation. The Wet Labs Phase II Project will add 4,500 SF of custom built additional area, intended to meet the most stringent industry standards.

The construction documents phase of the project is currently been completed; the estimated total project cost is $950,000 dollars. Half of these funds are funded by federal funds, through the Economic Development Agency (EDA) and the other half by the Cal Poly Pomona Foundation. The finished building will be leased for commercial and industry use only, and is expected to be available in 2009.

Statistical Information

Construction start date:
April 2009
Expected completion date:
Sept. 2009
Construction Cost:
$400,000
Equipment $83,000
Total Project Cost: $650,000
Gross sq. footage:
4500
Assignable sq. footage:
3850
% of project complete:
10%

Project Funding

  • Funding for this project is from Cal Poly Pomona Foundation Inc. and a matching grant from the Federal Economic Development Administration.

Progress of Major Construction Activities

  • Notice to proceed has been issued to TBC and is dated April 13, 2009.
  • Construction has formally started on April 20 and site activities are proceeding according to plan.
  • TBC Contractors are currently installing metal stud frames and electrical infrastructure.
  • The Lab’s furniture and equipment submittals have been submitted to the Owner for review and approval.
  • Long lead items such as HVAC equipment ands structural steel have been already reviewed and approved by the Project Architect.
  • Weekly meetings are being conducted at the site including CPPF, FD&C and Contractor.

Key/Critical Issues Currently Pending

  • Contractor to resubmit required Furniture and Equipment submittals for the Wet labs.
  • Contractor to cap off remaining open ducts and install VAV boxes to develop adequate back pressure to existing HVAC system at the building.

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance

  • NA at this time.