Contents
Cal Poly Pomona

March 2009 Updates

CTTI Wet Labs - Phase II

CTTI Building. Click to Zoom. Building infrastructure for new Wet Labs. Click to Zoom. Proposed Wet Lab Plan. Click to Zoom.
Parking lot and truncated domes will me modified to accommodate for recent DSA requirements. Click to Zoom. A modern  fume hood and an independent HVAC system will be installed at each wet lab. Click to Zoom. Existing wet lab is leased to private chemistry business for state of the art applications. Click to Zoom.

About This Project

The CTTI Wet Lab Phase II project is located at the intersection of Temple Ave. and South Campus Drive, at the Center for Training Technology & Incubation. The Wet Labs Phase II Project will add 4,500 SF of custom built additional area, intended to meet the most stringent industry standards.

The construction documents phase of the project is currently been completed; the estimated total project cost is $950,000 dollars. Half of these funds are funded by federal funds, through the Economic Development Agency (EDA) and the other half by the Cal Poly Pomona Foundation. The finished building will be leased for commercial and industry use only, and is expected to be available in 2009.

Statistical Information

Construction start date:
April 2009
Expected completion date:
Sept. 2009
Construction Cost:
$400,000
Equipment $83,000
Total Project Cost: $650,000
Gross sq. footage:
4500
Assignable sq. footage:
3850
% of project complete:
0%

Project Funding

  • Funding for this project is from Cal Poly Pomona Foundation Inc. and a matching grant from the Federal Economic Development Administration.

Progress of Major Construction Activities

  • 100% construction documents were approved by the Fire Marshal and by DSA.
  • The bid was opened on January 15th and the low bidder is TBC Contractors, with a total bid amount of $483,000 inclusive of the lab’s equipment.
  • Bid documentation and Contractor approval has been accepted by EDA. Covenant and legal documentation was secured.
  • Notice to proceed has been issued to TBC and is dated April 13, 2009
  • Preconstruction meeting was held on April 7, 2009.

Key/Critical Issues Currently Pending

  • Secure Economic Development Agency approval.
  • Contractor to start construction at the site by April 15th.

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance

  • NA at this time.