About This Project

The CTTI Wet Lab Phase II project is located at the intersection of Temple Ave. and South Campus Drive, at the Center for Training Technology & Incubation. The Wet Labs Phase II Project will add 4,500 SF of custom built additional area, intended to meet the most stringent industry standards.

The construction documents phase of the project is currently been completed; the estimated total project cost is $950,000 dollars. Half of these funds are funded by federal funds, through the Economic Development Agency (EDA) and the other half by the Cal Poly Pomona Foundation. The finished building will be leased for commercial and industry use only, and is expected to be available in 2009.

Statistical Information

Construction start date:
March 2009
Expected completion date:
Aug. 2009
Construction Cost:
$600,000
Equipment $90,000
Total Project Cost: $850,000
Gross sq. footage:
4500
Assignable sq. footage:
3850
% of design project complete:
100%

Progress of Major Construction Activities

  • Construction Documents are 100% completed.
  • 100% construction documents were approved by the Fire Marshal.

Key/Critical Issues Currently Pending

  • Secure Economic Development Agency approval.
  • Addendum #1 and #2 information will be integrated into a new set of construction documents.
  • Bid documents will be rebid and advertised by 12/12/08

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance

  • NA at this time.