July 2008 Updates

CTTI Wet Labs - Phase II

CTTI Building. Click to Zoom. Proposed Wet Lab Plan. Click to Zoom.

About This Project

The CTTI Wet Lab Phase II project is located at the intersection of Temple Ave. and South Campus Drive, at the Center for Training Technology & Incubation. The Wet Labs Phase II Project will add 4,500 SF of custom built additional area, intended to meet the most stringent industry standards.

The schematic design phase of the project has recently started; the estimated total cost is $1.0 million. Half of these funds are funded by federal funds, and the other half by the Cal Poly Pomona Foundation. The finished building will be leased for commercial and industry use only, and is expected to be available in 2009.

Statistical Information

Construction start date:
Oct. 2008
Expected completion date:
May 2009
Construction Cost:
$750,000
Total Project Cost: $950,000
Gross sq. footage:
4500
Assignable sq. footage:
N/A
% of project complete:
0%

Progress of Major Construction Activities

  • Construction Documents progress is 95% .
  • 95% construction documents were submitted to Fire Marshal and DSA for statutory approval.

Key/Critical Issues Currently Pending

  • Secure Fire Marshall permit
  • Secure DSA permit
  • Prepare Bid documents

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance

  • NA at this time.