About This Project

The CTTI Wet Lab Phase II project is located at the intersection of Temple Ave. and South Campus Drive, at the Center for Training Technology & Incubation. The Wet Labs Phase II Project will add 4,500 SF of custom built additional area, intended to meet the most stringent industry standards.

The schematic design phase of the project has recently started; the estimated total cost is $1.0 million. Half of these funds are funded by federal funds, and the other half by the Cal Poly Pomona Foundation. The finished building will be leased for commercial and industry use only, and is expected to be available in 2009.

Statistical Information

Construction start date:
August 2008
Expected completion date:
December 2008
Construction Cost:
$750,00
Total Project Cost: $1,000,000
Gross sq. footage:
4500
Assignable sq. footage:
N/A
% of project complete:
0%

Progress of Major Construction Activities

  • HMC firm was selected to provide architectural services
  • Schematic design started.

Key/Critical Issues Currently Pending

  • Secure Fire Marshall permit
  • Consolidate budget and construction scope of work

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance