Cal Poly Pomona

January 2011 Updates

CTTI Parking Lot Modification & Innovation Way III

West side of Building B prior to start of construction work 1/12/11. Click to Zoom. West side of Building B at the start of construction work 1/18/11. Click to Zoom. Work on new electrical conduits for the new parking lot pole lights on the north side of Building C.  Click to Zoom.
Asphalt removal new the new combined entry to CTTi and Innovation Village Phase IV. (1/18/11). Click to Zoom. Preparations for new curbs and channel gutter along north edge of CTTi (1/24/11). Click to Zoom. Preparation for new ADA ramps at Building B (1/24/11). Click to Zoom.

About This Project

Modification of the existing parking lot for the CTTi Complex is necessary for he proper alignment of the final section of the ne Innovation Way road that will connect Kellogg Drive and Temple Avenue thru the center of the Innovation Village Research Park. The parking lot modifications will afford the opportunity for the Foundation to maintain the required number of spaces required by the Innovation Village Guidelines and maintain the lease ability of the complex. The work will include the removal of several ornamental Pear Trees which will be replanted along Kellogg Drive near the main campus, new planters with more native plantings similar to those planted at the Phase III and Phase IV sites, new high efficiency parking lot lights to match those at the other phases and new asphalt paving. The final section of the Innovation Way road will match the other sections now completed and ready for full use. In addition infrastructure will be continued to afford connectivity of the CTTi Complex with the main campus and future connection with other utilities from the Temple Avenue edge of the Village. The work is being completed by Sully-Miller Contracting Company of Brea, California.

Statistical Information

Construction start date:
Jan 2011
Expected completion date:
May 2011
Construction Cost:
$653,600
Total Project Cost: $850,000
Gross sq. footage:
NA
Assignable sq. footage:
NA
% of project complete:
15%

Project Funding

  • Cal Poly Pomona Foundation Inc. and EDA Grant

Progress of Major Construction Activities

  • Site Survey and marking of Underground Utilities
  • Setting of temporary facilities and fences
  • Setting of the project Sign
  • Posting of directional signs to assist tenants of CTTi with maneuvering while under construction
  • Saw cutting and removal of concrete curbs, sidewalks and asphalt drive and parking lot.
  • Completion site landscape irrigation systems sleeves and tie-ins.
  • Removal of old parking light poles and bases
  • Installation of electrical feeder conduits for new light poles
  • Fine grade for new curbs and gutters and walkways in Phase One area.
  • Protection of remaining structures

Key/Critical Issues Currently Pending

  • Complete punch list and repairs.

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance

  • NA at this time.