February 2011 Updates

College of Business Administration (CBA)

Main Entrance View. Click to Zoom. Canopy framework near Building 162. Click to Zoom. Building 164 South Elevation. Click to Zoom.
AHU on Building 164 Rooftop. Click to Zoom. Steel Frame Canopy Entrance. Click to Zoom. Roofing installation on Building 164. Click to Zoom.

About This Project

The College of Business Administration will be located adjacent to the University’s Rose Garden on the present site of the Ornamental Horticulture (OH) Unit along University Drive. It will be a new three building complex ( Buildings 162,163 & 164). Building 164 will be a 3-story steel frame plastered structure for faculty/administration. Buildings 162 and 163 will be a 1-story and 2-story concrete masonry unit buildings. The placement of these three buildings will create an exterior landscaped courtyard which can serve as pre-function gathering space, quiet study space and special occasion meeting space for the College.

This project will add approximately 74,500 gross square feet and will include the installation of the state-of-the-art Learning Centered Technology Initiative equipment in all instructional and lecture classrooms. Data connectivity to the campus’ internet network will also be available throughout these offices, conference rooms and instruction classrooms.

Building 164 will house 115 faculty offices, department offices, conference rooms, multi-purpose room and support spaces. A food services facility will also be located on the ground floor. Building 163 will house five 83-station case-study type classrooms, two 35-station multi-mode classrooms, six 48-station classrooms & conference rooms. Building 162 will include two large lecture rooms, one with 201 stations. and one with 121 stations.

Statistical Information

Construction start date:
Feb 2010
Expected completion date:
Feb 2012
Construction Cost:
$30,306,102
Total Project Cost: $38,376,000
Gross sq. footage:
74,470
Assignable sq. footage:
49,078
% of project complete:
50%

Project Funding

  • Voter approved General Obligation Bond, Cal Poly Pomona Foundation Inc. and Private Donations

Progress of Major Construction Activities

  • Building 164: Ductwork, electrical, plumbing , door frames, partition wall stubs and exterior windows. Roofing complete
  • Building 163: Ductwork, electrical and plumbing. Roofing complete
  • Building 162: Ductwork , electrical and plumbing
  • Site: Steel entrance canopy.

Key/Critical Issues Currently Pending

  • Exterior plaster details mock up scheduled for early March.

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance

  • NA at this time.