December 2008 Updates

College of Business Administration (CBA)

Conceptual Site Plan. Click to Zoom. College of Business Administration Artist’s Rendering. Click to Zoom. Conceptual Main Courtyard Entrance. Click to Zoom.
Existing site looking north. Click to Zoom. Architect’s Wood Scaled Model of the College of Business. Click to Zoom. Existing Site - OH Unit. Click to Zoom.

About This Project

The College of Business Administration project will be located adjacent to the University’s Rose Garden on the present site of the Ornamental Horticulture (OH) Unit along University Drive. It will be a new complex consisting of three buildings (Wing A, B & C). Wing A will be a 3-story steel frame structure for faculty/administration. Wing B and C will be is a 1-story and 2-story buildings with concrete masonry units. The placement of these three buildings will create an exterior landscaped courtyard which can serve as pre-function gathering space.

This project will add approximately 75,000 gross square feet and will include the installation of the state-of-the-art Learning Centered Technology Initiative equipment in all instructional and lecture classrooms. Data connectivity to the campus’ internet network will also be available throughout these offices, conference rooms and instruction classrooms.

Wing A will house 117 faculty offices, department offices, conference rooms and support services spaces. A food services facility will also be located on the ground floor. Wing C is a 2-story concrete masonry unit classroom building that will house five case-study type classrooms, two multi-mode classrooms and break rooms.

Statistical Information

Construction start date:
March 2009
Expected completion date:
Pending
Construction Cost:
$32,913,000
Total Project Cost: $40,575,000
Gross sq. footage:
74,470
Assignable sq. footage:
49,078
% of project complete:
0%
Project suspended due to State Budget Crisis

Project Funding

  • Funding for this project is from Proposition 1D Bond Funds, Cal Poly Pomona Foundation Inc., and Private Donations.

Progress of Major Construction Activities

  • Asbestos/Lead Abatement started on Dec 16, 2008 and was completed on Jan 07, 2009

Key/Critical Issues Currently Pending

  • Bidding period started on Dec 15, 2008. The Gmax is supposed to be completed on Feb 10, 2009. This bidding process is currently on hold due to current State Budgetary Crisis.

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance

  • NA at this time.