November 2008 Updates

College of Business Administration (CBA)

Conceptual Site Plan. Click to Zoom. College of Business Administration Artist’s Rendering. Click to Zoom. Conceptual Main Courtyard Entrance. Click to Zoom.
Existing site looking north. Click to Zoom. Architect’s Wood Scaled Model of the College of Business. Click to Zoom. Existing Site - OH Unit. Click to Zoom.

About This Project

The College of Business Administration project will be located adjacent to the University’s Rose Garden on the present site of the Ornamental Horticulture (OH) Unit along University Drive. It will be a new complex consisting of three buildings (Wing A, B & C). Wing A will be a 3-story steel frame structure for faculty/administration. Wing B and C will be is a 1-story and 2-story buildings with concrete masonry units. The placement of these three buildings will create an exterior landscaped courtyard which can serve as pre-function gathering space.

This project will add approximately 75,000 gross square feet and will include the installation of the state-of-the-art Learning Centered Technology Initiative equipment in all instructional and lecture classrooms. Data connectivity to the campus’ internet network will also be available throughout these offices, conference rooms and instruction classrooms.

Wing A will house 117 faculty offices, department offices, conference rooms and support services spaces. A food services facility will also be located on the ground floor. Wing C is a 2-story concrete masonry unit classroom building that will house five case-study type classrooms, two multi-mode classrooms and break rooms.

Statistical Information

Construction start date:
March 2009
Expected completion date:
March 2010
Construction Cost:
$32,913,000
Total Project Cost: $40,575,000
Gross sq. footage:
74,470
Assignable sq. footage:
49,078
% of project complete:
0%

Progress of Major Construction Activities

  • Fencing completed.
  • Dept. of Finance issued approval to go to bid on Nov 18, 2008
  • AC Martin to issue bidding documents on Dec 08, 2008. Final back check in progress.

Key/Critical Issues Currently Pending

  • Asbestos/Lead Abatement in Dec 2008
  • Bidding period to start Dec 15, 2008 through Feb 10, 2009
  • Buildings only demolition in January of 2009
  • Department of Finance (DOF) approval to award in February of 2009

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance

  • NA at this time.