October 2008 Updates

College of Business Administration (CBA)

Conceptual Site Plan. Click to Zoom. College of Business Administration Artist’s Rendering. Click to Zoom. Conceptual Main Courtyard Entrance. Click to Zoom.
Building 126A Office Elevations. Click to Zoom. Architect’s Wood Scaled Model of the College of Business. Click to Zoom. Building 126C First Floor Classroom/Lecture Room Layout. Click to Zoom.

About This Project

The College of Business Administration project will be located adjacent to the University’s Rose Garden on the present site of the Ornamental Horticulture (OH) Unit along University Drive. It will be a new complex consisting of three buildings (Wing A, B & C). Wing A will be a 3-story steel frame structure for faculty/administration. Wing B and C will be is a 1-story and 2-story buildings with concrete masonry units. The placement of these three buildings will create an exterior landscaped courtyard which can serve as pre-function gathering space.

This project will add approximately 75,000 gross square feet and will include the installation of the state-of-the-art Learning Centered Technology Initiative equipment in all instructional and lecture classrooms. Data connectivity to the campus’ internet network will also be available throughout these offices, conference rooms and instruction classrooms.

Wing A will house 117 faculty offices, department offices, conference rooms and support services spaces. A food services facility will also be located on the ground floor. Wing C is a 2-story concrete masonry unit classroom building that will house five case-study type classrooms, two multi-mode classrooms and break rooms.

Statistical Information

Construction start date:
March 2009
Expected completion date:
March 2010
Construction Cost:
$32,913,000
Total Project Cost: $40,575,000
Gross sq. footage:
74,470
Assignable sq. footage:
49,078
% of project complete:
0%

Progress of Major Construction Activities

  • Division of the State Architect ( DSA) approved the 100% CD docs on 10/30/08.
  • Incorporate deductive alternate items into bidding documents. Final back check in progress.
  • Finalize Bidding Documents by Construction Manager at Risk (CM at Risk)
  • Request for scope change letter issued to Dept. of Finance for 11/14/08 SPWB meeting.

Key/Critical Issues Currently Pending

  • Site fencing to be installed by end of November of 2008 and surface demolition in December of 2008
  • Department of Finance (DOF) approval to go to bid

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance

  • NA at this time.