August 2008 Updates

Campus Wide Fire Alarm Upgrades

Building 92 OS&Y Valve. Click to Zoom. Building 89 OS&Y Valve. Click to Zoom. Building 89 Anti-Tamper Device. Click to Zoom.

Building 89 Post Indicator Valve. Click to Zoom. Building 67 Trench. Click to Zoom. Building 67 Trench Patch Work. Click to Zoom.

About This Project

The Fire Alarm Upgrades project consists of engineering and designing a new system that complies with all current applicable standards and codes, communicates and integrates with other campus fire alarm systems and any potential future fire alarm related upgrades. The buildings being upgraded are 1, 2, 6, 9, 13, 25, 29, 41 and 46. Due to good results, Buildings 67, 89, 89a, 89b and 92 have been added to the Fire Alarm System Upgrades on this Project. Last year, Buildings 7, 8 and 45 were completed.

Statistical Information

Construction start date:
April 19, 2007
Expected completion date:
Summer 2008
Construction Cost:
$1,765,000
Total Project Cost: $1,900,000
Gross sq. footage:
643,860
Assignable sq. footage:
389,322
% of project complete:
92%

Progress of Major Construction Activities

  • All main construction work is now complete.
  • State Fire Marshal has approved all the Buildings except for 89b.
  • Building 89b, rewire the flow device.
  • Minor patch and paint work remaining.

Key/Critical Issues Currently Pending

  • NA at this time.

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance

  • NA at this time.