About This Project

The Fire Alarm Upgrades project consists of engineering and designing a new system that complies with all current applicable standards and codes, communicates and integrates with other campus fire alarm systems and any potential future fire alarm related upgrades. The buildings being upgraded are 1, 2, 6, 9, 13, 25, 29, 41, 43 and 46. Due to good results, Buildings 67, 89 and 92 have been added to the Fire Alarm Upgrades for this year. There is also consideration on reprogramming the Fire Alarm System in Building 4. Last year, Buildings 7, 8 and 45 were completed.

Statistical Information

Construction start date:
April 19, 2007
Expected completion date:
Summer 2008
Construction Cost:
TBD
Total Project Cost: $1,900,000
Gross sq. footage:
643,860
Assignable sq. footage:
389,322
% of project complete:
88%

Progress of Major Construction Activities

  • Buildings 89 and 89a are ready for pretest.
  • Building 89 and 89a installation work is nearly complete and shall be pre-tested approximately in mid August.
  • Building 67 is near completion.
  • Building 92 installation work is starting on August 5th.

Key/Critical Issues Currently Pending

  • State Fire Marshal’s inspections pending.

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance

  • NA at this time.