The Fire Alarm Upgrades project consists of engineering and designing a new system that complies with all current applicable standards and codes, communicates and integrates with other campus fire alarm systems and any potential future fire alarm related upgrades. The buildings being upgraded are 1, 2, 6, 9, 13, 25, 29, 41, 43 and 46. Due to good results, Buildings 67, 89 and 92 have been added to the Fire Alarm Upgrades for this year. There is also consideration on reprogramming the Fire Alarm System in Building 4. Last year, Buildings 7, 8 and 45 were completed.

Statistical Information

Construction start date:
April 19, 2007
Expected completion date:
Summer 2008
Construction Cost:
TBD
Total Project Cost: $1,900,000
Gross sq. footage:
643,860
Assignable sq. footage:
389,322
% of project complete:
86%

Progress of Major Construction Activities

  • Buildings 67, 89, 89a and 92 are in progress.
  • Building 89 and 89a installation work is nearly complete and shall be pre-tested approximately August 1 st.
  • Building 67 installation work has begun.
  • Building 91 installation work expected to start the first part of August.

Key/Critical Issues Currently Pending

  • State Fire Marshal’s inspections pending.

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance

  • NA at this time.